Contracting

CONTRACTING

Delivering integrated contracting solutions for projects

  • Design, installation and operation of laboratories and factories

  •  
  •  
  • CONSTRUCTION AND COMMISSION OF ALUM. RECYCLING WASTE FACTORY/ JORUF Al NAJAF

 

Setting up and implementing stages for aluminum alloy production (belt conveyor the alum scrap for collection, preparation, shredding, iron removal, decoding, compacting cleaning, smelting, refining, alloying and casting)

Date: - 2019-2020

 

Location: -   BAGHDAD / IRAQ


  • Design, installation and operation of water purification and pumping stations

  •  
  • WATER FOWARDING SYSTEM (WFS) – SE. With Siemens energy
  •  
  •  

 

  1. Heat weld (butt weld) HDPE pipes 3”,4”,6”,8” inlet and outlet pipelines of MOE basket strainers for each of 5 units, (total length 1650 LM).
  2. Install QTY.6 horizontal water pump max. 9 bars with safety valve has setting on 8.5 bars to backflow to RO tank.
  3. Hydrostatic test for HDPE from outlet pump up to UCS inlet 3 “
  4. Install control panel with pressure switches and level transmitter sense through tank empty status.

         

 

Date: - 2022-2022

Location: -   BASRA/ IRAQ


Design, manufacture and installation of containers and steel structures (temporary and permanent)

 

INSTALL ENCLOSURES FOR UCS FORWARDING PUMP SKIDS- SE. With Siemens energy

 

 

  1. Supply and install steel structure frame (walls, roof, H beam for fixing (lifting device), sealed lateral slide door, Control panel movable door sand blast, paint)
  2. Supply and install isolated sandwich panel (4 Inch) for isolating Pump skid steel structure and control panel room.
  3. Supply and install Electric chain hoist 1.0 ton (DST-1S) – DAESAN Brand / South Korea) with accessories (Manual trolly, cable guideway)

     

Date: - 2023-2023

 

         Location: -   BASRA, BAGHDAD, KIRKUK / IRAQ


UPGRADING SFC, SEE systems FOR AL SADDER POWER PLANT

 

SE. With Siemens energy

 

 

1 – Replace the cabinets: SFC, SEE, and I&C.

2 – Laying and connecting the power and control cables.

3-  Civil and Mechanical work.

3 – Loop check for all.

 

Date: - 2024-2025

 

Location: -   BAGHDAD / IRAQ


  • I&C WORKS

  •  

    -UPS MAINTENANACE GAS POWER PLANT 
  •  

     

    Maintenance and commissioning of UPS1 & UPS 2 and 2 set of batteries, Functional test according to GUTOR Manual regards to:

    1. ON / OFF of UPS ,2. Battery charging (boost and floating) , 3. Battery capacity test , 4. Invertor fail and changeover test, 5. Bypass change over and functional test,6. Clear the alarm

         

Date: - 2023-2024

 

Location: -   BASRA/ IRAQ


  • (Elictrical+I&C+Mechanical) Works

  •  
  •  

    PULSE CLEANING AIR INTAKE GAS TURBINE
  •  

     

    1. HMI replaced with new one and date downloaded from old HMI and upload to new one
    2. Regulator disassembled and cleaned and pressure indicator changed with new one and installed and outlet pressure
    3. Sequence started manually and all pulse and solenoid monitored any abnormal factor and faulty case

     

Date: - 2023

 

Location: -   Rumaila PP / BASRA / IRAQ


UPGRADE BOGE AIR SYSTEM FOR GAS TURBINE UNIT QTY.5

 

 

Modification for auto change over between BOGE & HANSHIN (main compressed air unit) for qty.5 of GTGs includes:

  1. Install pressure transmitter with necessary fitting and valves
  2. install normally open solenoid valve
  3. install PID controller with power supply
  4. Parameter adjustment and functional test report
  5. Replaced Refrigerant of dryer, Micro filter drain valve, controller battery voltage, Condensation drain valve

 

Date: - 2023

 

Location: -   Rumaila PP/ BASRA / IRAQ


Civil works

 

Excavation, filling, pouring and paving a street in the city

 

 

Date: - 2021

 

Location: -   NAJAF / IRAQ

Image